Sewer Construction Update:

MASTER PLAN PRIORITY I PHASE 2 PROJECT TO BEGIN SPRING 2013 - click here for a map of project locations.

Project Description

The Master Plan Priority 1 Phase 2 Project is a collection of 12 critical sewer repairs at five locations. These critical repairs are typically repairs of defects that are too severe to be repaired with spot repairs. The MPP1-P2 project will consist of constructing approximately 1,500 feet of replacement sewers, 200 feet of new sewers and abandoning 1,100 feet of existing sewers. At four of the five project locations, a new 8-inch diameter sewer will replace existing 6-inch diameter sewer to bring these sewer lines in conformance with current District standards. One of the five project locations consist of replacing the existing 12-inch diameter sewer with new 12-inch diameter sewer. This project will also include the construction of nine new sanitary sewer manholes (SSMH), reshape bottoms of nine existing, and abandoning two existing manholes.

Import Dates

December 12, 2012 - Start of Bid Advertisement
January 7, 2013 at 2:00 pm - Pre-Bid Meeting
January 22, 2013 at 10:00 am - Bid Opening
March 2013 - Start of Construction
June 2013 - End of Construction

Contractor

Pending

Road Impacts

While we don't anticipate any road closures for this project, please check back during the construction period for up to date road impact information.

 

MASTER PLAN REPAIRS PROJECT TO BEGIN SUMMER 2013 - click here for a map of project locations.

Project Description

The Master Plan Repairs Project is a collection of approximately 70 repairs at various locations throughout Castro Valley. These repairs consist of both spot repairs (typically 4-6 feet in length) and full line replacements. The MP Repair Project consists of 6” and 8” sewer repair/replacement. Typical spot repairs take about 2 days to complete while line replacements typically take about 2 weeks.

Import Dates

January-March – Project design and preparation
April 3, 2013 - Start of Bid Advertisement
June-July 2013 - Start of Construction
December 2013 - End of Construction

Contractor

Pending

Road Impacts

While we don't anticipate any road closures for this project, please check back during the construction period for up to date road impact information.

 

The  District continues to implement sewer replacements and upgrades identified in the Wastewater Collection System Master Plan to reduce the risk of sewer overflows

 

Wastewater Master Plan Environmental Documents

Master Plan(48.9M)

Castro Valley Blvd Streetscape Sewer Project Initial Study

Castro Valley Blvd Streetscape Sewer Project Mitigated Negative Declaration

For project information, please contact the District at (510) 537-0757.