Recycling Guide  
  Frequently Asked Questions  
  Recycled Art Contest 
  Solid Waste Department
  Earth Day 2007
  Description of Services  
  Lateral Grants  
  Permits and Fees  
  Where's My Lateral?  
  Standard Specifications  
  Projects  
  Easements 
  Annual Report 
  Calendar of Events  
  Board of Directors  
  Board Business  
  District Newsletter  
  Financial Information  
  General Information  
  Press Releases 
  Employment Opportunities
  Community Advisory Committee
 
 
Projects

[from a April 23, 2007 staff memo to the Board of Directors]
  1. Aerial Pipes Retrofit - Staff has contacted 9 structural/soils engineers to examine and evaluate eight locations of aerial pipes – above ground and/or crossing over a creek – and provide a detailed study for a possible retrofit project. The goal is to protect those critical locations from damage during an earthquake. The District received three proposals that are currently being reviewed. The two criteria used to select the best consultant are qualifications and cost. A recommendation will be made in the June Board meeting.


  2. Sampling at Flume - Bi-weekly composite samples were taken during the month of April and delivered to the City of San Leandro for independent testing and analysis. Mercury analysis was performed as well.


  3. Overflow Tank, Pump Station No. 3 - Staff has finalized the plans and specifications for a 5000-gallon tank that will be installed to serve as emergency detention containment in case of failure to Pump Station #3. Specifications to repave the entire site have also been added. The District has allocated $20,000 to the installation of this tank in its 2006/2007 budget. Engineer’s cost estimate to repave the site is $15,000 for a total of $35,000 for this project. Staff is currently in the process of contacting several contractors to solicit a bid in compliance with the latest Public Contracting Procedures.


  4. Wastewater Collection System Master Plan - Staff has contacted all utility companies within Castro Valley and received data pertaining to their respective lines in the vicinity of this project. Staff is currently preparing the plans and specifications. The District has allocated $606,000 for this project in its 06/07 budget. The bid package for this project should be ready by the June 2007 Board meeting.


  5. FOG Program - The enforcement of the FOG program has commenced its preliminary phase in the month of April, which involves an initial inspection of all FSE facilities within CVSD jurisdiction. To date, 12 facilities have been inspected for compliance, 124 facilities remaining.



  6. CVSD Code - Engineering staff has finished reviewing the Code. The proposed changes to the Code will be presented to the Board for approval in its June 2007 meeting.


  7. Small Point-Repair Project – Ortiz Construction, Inc. has repaired a total of 6 locations on the project list with 12 remaining. It is anticipated that all locations will be completed within approximately two months.


  8. New Office Space - Plans to convert the shop in the parking lot into office space for the maintenance crew and engineering technicians have been finalized. Staff is in the process of advertising the project.


  9. Lift Station Upgrade - Engineering staff has completed a survey of all pump stations and has put together recommendations for a bypass mechanism to be installed at lift station No. 1, 3, 5, 8, 9, and 11 in case of a failure to the pumps. The District has set aside $31,000 for this project in its 06/07 budget. The upgrades include installing a 4” flange that will allow making a direct connection to the discharge pipe and bypassing the pump when it fails. Staff is in the process of hiring a pump specialist from Dodson Engineered Products to peer review and validate staff recommendations.


  10. OER Trailer - Equipment has been purchased and miscellaneous items have been installed in the Overflow Emergency Response Trailer. The project was completed $900 below budget.


  11. Inspections - Staff has performed inspections of five repair permits and three new connections in April.

Last updated 05.30.07

Castro Valley Sanitary District
21040 Marshall Street
Castro Valley, CA 94546-6020
Phone: (510) 537-0757 | Fax: (510) 537-1312 | Email: info@cvsan.org